March 29, 2024, 5:06 pm


Staff Correspondent

Published:
2020-10-06 08:55:40 BdST

Payra power plant ready for full-fledged operation


The 1,320 MW coal-fired Payra power plant in Patuakhali district's Kalapara upazila is ready to operate at full blast.

Officials said the second unit of the plant, a joint venture between Bangladesh and China, has attained its generation capacity of 660 MW over the past three months and is now ready for commercial operation.

"The second unit is ready. We'll soon put forward our proposal to the state-owned Power Bangladesh Development Board (PBDB) to start operation," Shah Abdul Maula, project director of Bangladesh-China Power Company Limited (BCPCL), said.

BCPCL, a joint venture between state-owned North-West Power Generation Company Bangladesh Limited (NWPGCL) and China National Machinery Import & Export Corporation, has set up the plant at $2.0 billion as part of a development partnership.

After undergoing test runs for about five months, the first unit of the Payra power plant started commercial operation in May this year.

And if both the units are allowed to operate simultaneously, the plant will jointly generate 1320 MW electricity, thus setting a milestone in the country's power sector. So far,450 MW of power has been generated from a single power plant in Bangladesh.

Though Power Transmission Company of Bangladesh (PGCB) has recently undertaken a number of transmission projects to facilitate evacuation of electricity from the Payra power plant project, officials are not hopeful of getting a nod for simultaneous operation of the two units.

"This is because transmission lines are not yet synchronised. In such a case, we will go for alternative operation of the two units," an official said.

These transmission projects include construction of 160km 400kV double circuit line from Payra plant to Gopalganj, 164.6 km Aminbazar-Mawa-Gopalganj-Mongla 400 kV double circuit line and 9.4 km river-crossing line close to Padma Bridge.

PGCB officials said all these projects are being implemented targeting the power evacuation from both the Payra and Rampal plants and these will cost about Tk 46.50 billion, of which Tk 32.94 billion will be spent on Payra plant transmission facilities.

However, the 9.4 km river-crossing line close to Padma Bridge has not been progressing in an expected pace, which is creating an obstacle for evacuation of entire electricity from the Payra power plant, officials said.

Admitting the delay, PGCB managing director Golam Kibria said the deadline to implement all the Payra-linked transmission projects is March 2021. "But the delay in Padma Bridge work due to Covid-19 could push the deadline to December next year."

Unauthorized use or reproduction of The Finance Today content for commercial purposes is strictly prohibited.


Popular Article from National